GAQM
CSM-001 · Question #138
Which role in Scrum is responsible for Return On Investment (ROI)?
The correct answer is D. Product Owner. See the full explanation below for the reasoning.
Question
Which role in Scrum is responsible for Return On Investment (ROI)?
Options
- AScrum Development Team
- BScrum Master
- CNone of the above
- DProduct Owner
How the community answered
(50 responses)- A8% (4)
- B4% (2)
- C6% (3)
- D82% (41)
Community Discussion
No community discussion yet for this question.