Which role in Scrum is responsible to prioritize Product Backlog?
The correct answer is C. Product Owner. See the full explanation below for the reasoning.
Question
Which role in Scrum is responsible to prioritize Product Backlog?
Options
- AScrumMaster
- BDevelopment team
- CProduct Owner
- DLead Auditor
How the community answered
(56 responses)- A16% (9)
- B7% (4)
- C73% (41)
- D4% (2)