You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current taskin switching from RUP to Scrum is to define how long the Sprint cycle should be. In what…
The correct answer is C. A fixed amount of days. See the full explanation below for the reasoning.
Question
You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current taskin switching from RUP to Scrum is to define how long the Sprint cycle should be. In what units of time shouldyou define the sprint cycle?
Options
- AA fixed amount of months
- BA fixed amount of weeks, excluding holidays
- CA fixed amount of days
- DA fixed amount of hours
How the community answered
(47 responses)- A9% (4)
- B15% (7)
- C72% (34)
- D4% (2)