CSM-001 · Question #122
What happens when allcommitteditems(requirements) are not completed at the end of the Sprint?
The correct answer is C. They return to the product backlog. See the full explanation below for the reasoning.
Question
What happens when allcommitteditems(requirements) are not completed at the end of the Sprint?
Options
- AThe Sprint duration is extended
- BThe tasks are determined to be unnecessary
- CThey return to the product backlog
- DNone of the above
How the community answered
(30 responses)- A17% (5)
- B7% (2)
- C73% (22)
- D3% (1)
Community Discussion
No community discussion yet for this question.