A _______ is created during the first half of the Sprint planning meeting and a ____ is created during the second half of the Sprint planning meeting?
The correct answer is A. Sprint Backlog, collection of tasks. See the full explanation below for the reasoning.
Question
A _______ is created during the first half of the Sprint planning meeting and a ____ is created during the second half of the Sprint planning meeting?
Options
- ASprint Backlog, collection of tasks
- BProduct Backlog, collection of tasks
- CSprint Goal, Sprint Backlog
- DProduct Backlog, Sprint Backlog
How the community answered
(57 responses)- A70% (40)
- B9% (5)
- C5% (3)
- D16% (9)