CRISC · Question #83

During a risk assessment, a key external technology supplier refuses to provide control design and effectiveness information, citing confidentiality concerns. What should the risk practitioner do…

The correct answer is C. Review the supplier's contractual obligations. When a key external technology supplier refuses to provide control information during a risk assessment, the risk practitioner's immediate next step should be to review the existing contractual agreements.

Submitted by carter_n· Apr 18, 2026IT Risk Assessment

Question

During a risk assessment, a key external technology supplier refuses to provide control design and effectiveness information, citing confidentiality concerns. What should the risk practitioner do NEXT?

Options

  • AEscalate the non-cooperation to management
  • BExclude applicable controls from the assessment.
  • CReview the supplier's contractual obligations.
  • DRequest risk acceptance from the business process owner.

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    72% (21)
  • D
    17% (5)

Why each option

When a key external technology supplier refuses to provide control information during a risk assessment, the risk practitioner's immediate next step should be to review the existing contractual agreements.

AEscalate the non-cooperation to management

Escalating non-cooperation to management is premature until it's confirmed that the supplier has a contractual obligation they are failing to meet.

BExclude applicable controls from the assessment.

Excluding applicable controls from the assessment would create a significant gap in the risk analysis and should only be considered as a last resort.

CReview the supplier's contractual obligations.Correct

Before taking any further action, the risk practitioner must review the contractual agreement between the organization and the supplier to determine if the supplier is obligated to provide the requested control design and effectiveness information. This step clarifies whether the supplier is non-compliant with the contract or if such information sharing was never part of the agreement, informing subsequent actions.

DRequest risk acceptance from the business process owner.

Requesting risk acceptance before determining the supplier's obligations might prematurely accept an unknown risk and bypass potential contractual remedies.

Concept tested: Third-party risk management, contractual review

Source: https://learn.microsoft.com/en-us/azure/security/fundamentals/assurance-third-party-agreements

Topics

#Third-party risk#Vendor management#Risk assessment#Contractual obligations