nerdexam
Isaca

CRISC · Question #215

An internal audit report reveals that a legacy system is no longer supported Which of the following is the risk practitioner's MOST important action before recommending a risk response'

The correct answer is B. Assess the potential impact and cost of mitigation. Before recommending a risk response for an unsupported legacy system, the risk practitioner must first assess the potential impact of the risk and the associated costs of various mitigation options.

Submitted by miguelv· Apr 18, 2026IT Risk Assessment

Question

An internal audit report reveals that a legacy system is no longer supported Which of the following is the risk practitioner's MOST important action before recommending a risk response'

Options

  • AReview historical application down me and frequency
  • BAssess the potential impact and cost of mitigation
  • Cidentify other legacy systems within the organization
  • DExplore the feasibility of replacing the legacy system

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    80% (35)
  • C
    7% (3)
  • D
    11% (5)

Why each option

Before recommending a risk response for an unsupported legacy system, the risk practitioner must first assess the potential impact of the risk and the associated costs of various mitigation options.

AReview historical application down me and frequency

Reviewing historical downtime is useful but does not directly quantify the potential impact of *future* risks specific to an unsupported system or the costs of its mitigation.

BAssess the potential impact and cost of mitigationCorrect

Assessing the potential impact of the unsupported system's vulnerabilities and the costs associated with various risk responses (e.g., replacement, isolation, enhanced monitoring, or acceptance) is a fundamental step to formulate an appropriate, cost-effective recommendation. This analysis provides the necessary context for informed decision-making regarding the risk response.

Cidentify other legacy systems within the organization

Identifying other legacy systems is a broader inventory task, which does not directly address the immediate and specific risk presented by *this* unsupported system.

DExplore the feasibility of replacing the legacy system

Exploring replacement feasibility is a potential risk response, but this action should logically follow a thorough assessment of impact and mitigation costs to determine if replacement is the optimal path.

Concept tested: Risk assessment before response

Source: https://csrc.nist.gov/publications/detail/sp/800-30/rev-1/final

Topics

#Risk assessment#Impact analysis#Cost-benefit analysis#Risk response preparation

Community Discussion

No community discussion yet for this question.

Full CRISC Practice