nerdexam
Isaca

CRISC · Question #371

Which of the following provides the MOST useful input to the development of realistic risk scenarios?

The correct answer is D. Risk events. Realistic risk scenarios are best developed by analyzing actual historical incidents and failures that have occurred within an organization.

Submitted by tyler.j· Apr 18, 2026IT Risk Assessment

Question

Which of the following provides the MOST useful input to the development of realistic risk scenarios?

Options

  • ABalanced scorecard
  • BRisk appetite
  • CRisk map
  • DRisk events

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    7% (2)
  • C
    3% (1)
  • D
    87% (26)

Why each option

Realistic risk scenarios are best developed by analyzing actual historical incidents and failures that have occurred within an organization.

ABalanced scorecard

A balanced scorecard is a strategic performance management tool, not a direct input for specific risk scenario development.

BRisk appetite

Risk appetite defines the level of risk an organization is willing to accept, which guides responses but doesn't detail specific scenarios.

CRisk map

A risk map visually represents risks based on likelihood and impact, which is an output of risk assessment, not an input for scenario development.

DRisk eventsCorrect

Risk events are actual occurrences of risks materializing, providing concrete data and examples of how vulnerabilities can be exploited or threats can manifest. This historical data is invaluable for creating realistic scenarios that reflect real-world threats and impacts, informing the likelihood and consequence components of risk.

Concept tested: Risk scenario development inputs

Source: https://www.isaca.org/resources/isaca-journal/2012-volume-6/risk-scenarios-making-them-meaningful