CRISC · Question #460
Which of the following should be done FIRST when a new risk scenario has been identified
The correct answer is D. Identify the risk owner. When a new risk scenario has been identified, the first step is to identify the risk owner, as they are accountable for managing that specific risk.
Question
Which of the following should be done FIRST when a new risk scenario has been identified
Options
- AEstimate the residual risk.
- BEstablish key risk indicators (KRIs).
- CDesign control improvements.
- DIdentify the risk owner.
How the community answered
(38 responses)- A8% (3)
- B3% (1)
- C3% (1)
- D87% (33)
Why each option
When a new risk scenario has been identified, the first step is to identify the risk owner, as they are accountable for managing that specific risk.
Estimating residual risk comes after inherent risk assessment and considering potential controls, which can only happen effectively once ownership is established and initial risk treatment considered.
Establishing Key Risk Indicators (KRIs) is part of monitoring the risk, which occurs after the risk has been identified, assessed, and treatment strategies (including ownership) are in place.
Designing control improvements is a risk treatment step that occurs after the risk is identified, assessed, and an owner is assigned to lead the treatment effort.
Identifying the risk owner is foundational to effective risk management. The owner is accountable for the risk and its treatment, making this the crucial first step before further analysis or control design can proceed responsibly. Without an owner, there's no clear accountability for managing the risk.
Concept tested: Risk ownership assignment
Topics