nerdexam
Isaca

CRISC · Question #459

Which of the following is the BEST approach when a risk treatment plan cannot be completed on time?

The correct answer is B. Implement compensating controls until the preferred action can be completed. When a risk treatment plan cannot be completed on time, implementing compensating controls is the best approach to temporarily manage the risk.

Submitted by valeria.br· Apr 18, 2026Risk Response and Reporting

Question

Which of the following is the BEST approach when a risk treatment plan cannot be completed on time?

Options

  • AReplace the action owner with a more experienced individual.
  • BImplement compensating controls until the preferred action can be completed.
  • CChange the risk response strategy of the relevant risk to risk avoidance.
  • DDevelop additional key risk indicators (KRIs) until the preferred action can be completed.

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    74% (20)
  • C
    15% (4)
  • D
    4% (1)

Why each option

When a risk treatment plan cannot be completed on time, implementing compensating controls is the best approach to temporarily manage the risk.

AReplace the action owner with a more experienced individual.

Replacing the action owner might address a performance issue, but it does not immediately manage the risk exposure caused by the delay in the treatment plan itself.

BImplement compensating controls until the preferred action can be completed.Correct

Compensating controls provide an interim solution to reduce risk exposure when primary controls are delayed or cannot be fully implemented. They act as temporary measures to maintain an acceptable level of risk until the preferred, permanent treatment plan can be completed.

CChange the risk response strategy of the relevant risk to risk avoidance.

Changing the risk response strategy to avoidance means eliminating the risk entirely, which might not be feasible or desirable and is a fundamental change in strategy, not a temporary solution for a delay.

DDevelop additional key risk indicators (KRIs) until the preferred action can be completed.

Developing additional Key Risk Indicators (KRIs) helps monitor risk, but it does not actively treat or reduce the risk itself while the primary treatment plan is delayed.

Concept tested: Compensating controls

Topics

#Risk treatment#Compensating controls#Risk response#Action plan management

Community Discussion

No community discussion yet for this question.

Full CRISC Practice