Which of the following should be the FIRST consideration when establishing a new risk governance program?

The correct answer is C. Embedding risk management into the organization. The first consideration when establishing a new risk governance program should be embedding risk management into the organization's culture and operations. This foundational step ensures that risk management becomes an integral part of decision-making and business processes.

Submitted by naveen.iyer· Apr 18, 2026Governance

Question

Which of the following should be the FIRST consideration when establishing a new risk governance program?

Options

  • ADeveloping an ongoing awareness and training program
  • BCreating policies and standards that are easy to comprehend
  • CEmbedding risk management into the organization
  • DCompleting annual risk assessments on critical resources

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    89% (33)
  • D
    3% (1)

Why each option

The first consideration when establishing a new risk governance program should be embedding risk management into the organization's culture and operations. This foundational step ensures that risk management becomes an integral part of decision-making and business processes.

ADeveloping an ongoing awareness and training program

Developing awareness and training is an important component of embedding risk management, but not the first overarching consideration for establishing the program itself.

BCreating policies and standards that are easy to comprehend

Creating policies and standards is a necessary step, but it follows the strategic decision to embed risk management and define its scope.

CEmbedding risk management into the organizationCorrect

Establishing a new risk governance program requires it to be integrated into the organization's strategic objectives, culture, and day-to-day operations rather than being a standalone activity. Embedding risk management ensures that it is considered at all levels and in all decision-making processes from the outset, providing a strong foundation for the program's success and sustainability.

DCompleting annual risk assessments on critical resources

Completing annual risk assessments is an operational activity of an established risk management program, not the initial consideration for setting up the governance framework.

Concept tested: Risk governance program establishment foundation

Topics

#Risk Governance Program#Program Establishment#Risk Management Integration#Organizational Embedding

Community Discussion

No community discussion yet for this question.

Full CRISC Practice