Question
The software version of an enterprise's critical business application has reached end-of-life and is no longer supported by the vendor. IT has decided to develop an in-house replacement application. Which of the following should be the PRIMARY concern?
Options
- AThe system documentation is not available.
- BEnterprise risk management (ERM) has not approved the decision.
- CThe board of directors has not approved the decision.
- DThe business process owner is not an active participant.
Unlock CRISC to see the answer