- Question #51Data Collection and Use
In an analysis of variance, which of the following distributions is the basis for determining whether the variance estimates are all from the same population?
ANOVAF distributionvariance estimationstatistical testing - Question #52Data Collection and Use
Data collection for a failure reporting, analysis, and corrective action system is important. The control of input data is BEST determined by:
FRACASdata collection controlfailure reportingdata quality - Question #53System Reliability
Which answer mathematically expresses the reliability of an active parallel system in which all component reliabilities are unequal?
parallel system reliabilityredundancy mathinclusion-exclusion principlesystem reliability formula - Question #54Life Cycle Reliability Engineering
System and cost effectiveness analysis outputs:
cost effectiveness analysistrade-off decisionssystem performance balancedesign optimization - Question #55Life Cycle Reliability Engineering
Reliability objectives and requirements should be set in which of the following life cycle phases?
life cycle phasesreliability requirementsconcept phasereliability objectives - Question #56System Reliability
According to the Arrhenius Model, the expected life of an electronic component should:
Arrhenius modeltemperature accelerationcomponent lifethermal stress - Question #57Data Collection and Use
Which of the following failures would probably be considered a chargeable reliability failure?
chargeable failurefailure classificationreliability accountingunverified failure - Question #58Reliability in Design and Development
In the Taguchi design methodology, what are noise factors?
Taguchi methodnoise factorsrobust designoutput variation - Question #59Reliability in Testing
A reliability test of 12 pumps is terminated at 1000 hours. There were 5 failures as follows, what is the median rank % for the 4th failure ?
median rankWeibull analysiscensored testingreliability estimation - Question #60Leadership and Management
The use of PERT requires:
PERTproject schedulingnetwork analysisactivity time estimation - Question #61Life Cycle Reliability Engineering
Reliability Growth is:
reliability growthDuane modelAMSAAmathematical modeling - Question #62System Reliability
As a result of improper machining, a gear-tooth in a vehicle's transmission breaks causing the transmission to lock up and the vehicle to crash, injuring the driver. The failure mo...
failure modeFMEAfailure analysiscause vs effect - Question #63Life Cycle Reliability Engineering
Which of the following is the reason the bathtub curve has an increasing failure rate during the wear-out period?
bathtub curvewear-out periodfailure rateuseful life - Question #64System Reliability
What is the reliability of this system? Where component reliabilities, A = 0.80 B = 0.95 C = 0.82 D = 0.85 E = 0.75
system reliabilityreliability block diagramseries-parallel systemscomponent reliability - Question #65Data Collection and Use
50 resisters from a lot of 75,000 were tested. The average was 3,306 ohms with a variance of 21,609 ohm 2 . From this information, we may conclude with 99% confidence, that at leas...
tolerance intervalsconfidence intervalstatistical samplingnormal distribution - Question #66Life Cycle Reliability Engineering
The hazard function is:
hazard functionconditional probabilityfailure ratereliability mathematics - Question #67Reliability in Design and Development
The influence of FMEA on reliability is maximized at which of the following stages of development?
FMEAdesign stagereliability programfailure prevention - Question #68System Reliability
Your customer required a paper cutting machine with these specifications: Speed : 100m/minute; Cutting width : 47 inches; Good product : 99% You deliver a machine to this customer...
reliability requirementsspecification compliancecustomer requirementsfailure classification - Question #69Reliability in Testing
A field test may be considered satisfactory if:
field testingoperational readinesstest evaluationhuman factors - Question #70Data Collection and Use
In the binomial expression:
binomial distributionprobability theorystatistical mathematicsexpansion - Question #71System Reliability
The probability of an accident for the head event "H" given below is:
fault tree analysisprobability calculationaccident probabilitysystem safety - Question #72Reliability in Design and Development
Which of the following is an analytical approach used during the manufacturing process where process conditions are changed systematically for the purpose of determining modificati...
statistical process controlprocess improvementmanufacturing reliabilityanalytical methods - Question #73Reliability in Testing
All of the following are purposes of a production reliability assurance test (PRAT) EXCEPT
PRATproduction reliabilityreliability testingmanufacturing quality - Question #74Leadership and Management
From a company's point of view, which of the following costs would be LEAST appropriate for determining the cost of reliability?
reliability costscost classificationprogram managementwarranty cost - Question #75Reliability in Design and Development
The rated breaking strength of a suspension bridge cable is 150,000 pounds. An example using this cable in a derated condition is which of the following?
deratingstress-strengthdesign margincomponent rating - Question #76Data Collection and Use
In 4 flips of a coin the probability of two heads and two tails (in any order) is:
binomial probabilitycombinatoricsprobability calculationdiscrete distributions - Question #77Reliability in Design and Development
Which of following is NOT elements of risk priority number for FMEA?
FMEArisk priority numberRPNseverity detection occurrence - Question #78System Reliability
What is the reliability of the power switching system schematic on the left after 30,000 hours ? The electric utility primary power system (A) has a failure rate of 0.00001 failure...
standby redundancysystem reliabilityexponential distributionimperfect switching - Question #79Reliability in Testing
A primary purpose of burn-in testing of parts is to
burn-in testinginfant mortalityscreening testparts reliability - Question #80System Reliability
Develop the fault tree analysis for a candy dispensing machine. There are two contributing subsystems, both of them must fail for the system to fail. The electronic release has Pf...
fault tree analysisAND gateprobability of failuresystem safety - Question #81Reliability in Design and Development
The techniques of design control are:
design controlreliability engineeringindustry applicabilitygeneral application - Question #82System Reliability
What is this system`s reliability at 3000 hours? MTBFs for the components are : A = 2500 hours B = 3700 hours C = 2000 hours D = 4000 hours.
system reliabilityMTBFexponential distributionseries system - Question #83Leadership and Management
The continuous improvement process can be guided by several techniques. Which of the following is the BEST approach?
continuous improvementPDCA cyclequality toolsprocess improvement - Question #84Reliability in Design and Development
The department having the authority to sign all deviations pertaining to the design of the product is normally:
design controldeviation authoritydesign engineeringorganizational roles - Question #85System Reliability
Given mean-time-to-failure of 200 hours for each of two components, what is the probability of system failure if both components operate in parallel for one hour?
parallel redundancyfailure probabilityactive redundancyreliability calculation - Question #86Data Collection and Use
Which of the following is a primary concern for a reliability engineer who uses publicly available sources for mechanical part-failure rates?
failure rate datadata sourcespart failure ratesdata applicability - Question #87Reliability in Testing
Which answer correctly describes the experimental design on the left?
Graeco-Latin squareexperimental designDOEblocking - Question #88Life Cycle Reliability Engineering
Weibull analysis is a way to quickly and easily analyze field data or interval test data. The limits of the use of this technique include having a good estimate for the:
Weibull analysisshape parameterfield datalife data analysis - Question #89Reliability in Testing
The proper software tool for software development projects can help reduce test time. The software tools used to measure internal test coverage are called.
software testingtest coveragetest harnesssoftware reliability - Question #90Reliability in Design and Development
Which of the following statements is TRUE about human factor points?
human factorsdesign phasereliability designergonomics - Question #91System Reliability
System-safety analytical techniques include all EXCEPT:
system safetyfault tree analysishazard analysissafety analysis - Question #92Reliability in Design and Development
Design plans are BEST developed for product reliability with significant input from which of the following?
reliability planningcross-functional teamdesign developmentproject management - Question #93Maintainability and Availability
Maintenance times on simple with straightforward repair will fit which of the following distributions?
maintenance time distributionnormal distributionrepair timemaintainability - Question #94System Reliability
What is the failure rate of a system composed of three components, each of which can cause a system failure, and which have the following information?
failure rateseries systemsystem failure ratecomponent reliability - Question #95Reliability in Testing
Failure occur on a system at 75, 79, 83, 85 hours. Assuming normality, one sided and unbiased the lower tolerance limit for 95% reliability with 90% confidence for this sample is:
tolerance limitsnormal distributionreliability confidencestatistical tolerance - Question #96Reliability in Testing
A key distinction between Taguchi designed experiments and classical designed experiments is that Taguchi designs
Taguchi methodsexperimental designDOErandomization - Question #97Reliability in Testing
To achieve 96 percent reliability at a 90 percent confidence level:
reliability demonstrationconfidence levelsample sizebinomial statistics - Question #98System Reliability
In a certain application, two identical transducers are used to measure the vacuum in a system. The system is considered to have failed if either of the vacuums read by the transdu...
reliability block diagramseries configurationsystem configurationfailure logic - Question #99Life Cycle Reliability Engineering
A small sample from a product population is subjected to multiple levels of elevated stress. Which of the following could be used to model the life of the product?
accelerated life testinginverse power lawstress modelslife modeling - Question #100Data Collection and Use
Laboratory tests of a new polymer prototype yielded the following proportions of a critical compound: 4.2 ppm, 4.1 ppm, 4.7 ppm, 4.9 ppm, 5.3 ppm What is the sample standard deviat...
sample standard deviationdescriptive statisticsstatistical calculationsample statistics