CRE Question #54: Real Exam Question with Answer & Explanation

The correct answer is A. Can be used to determine the best balance of system performance, cost and schedule.. See the full explanation below for the reasoning.

Question

System and cost effectiveness analysis outputs:

Options

  • ACan be used to determine the best balance of system performance, cost and schedule.
  • BDo not guide trade-off decisions.
  • CIn most cases will not identify the degree to which innovations should be pursued.
  • DWill not guide preliminary design features.