CRE · Question #77

Which of following is NOT elements of risk priority number for FMEA?

The correct answer is B. Catastrophic. You've hit your weekly limit · resets 5am (America/New_York)

Reliability in Design and Development

Question

Which of following is NOT elements of risk priority number for FMEA?

Options

  • ASeverity
  • BCatastrophic
  • CProbability
  • DDetection

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    86% (31)
  • C
    6% (2)
  • D
    6% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#FMEA#risk priority number#RPN#severity detection occurrence