nerdexam
ASQ

CRE · Question #60

CRE Question #60: Real Exam Question with Answer & Explanation

The correct answer is C. Time estimates for each activity in the network.. See the full explanation below for the reasoning.

Question

The use of PERT requires:

Options

  • AThe critical path to be known in advance.
  • BSlack times to be added to the critical path.
  • CTime estimates for each activity in the network.
  • DLess data than a Gantt chart.

Community Discussion

No community discussion yet for this question.

Full CRE Practice