The use of PERT requires:
The correct answer is C. Time estimates for each activity in the network. You've hit your weekly limit · resets 5am (America/New_York)
Leadership and Management
Question
The use of PERT requires:
Options
- AThe critical path to be known in advance.
- BSlack times to be added to the critical path.
- CTime estimates for each activity in the network.
- DLess data than a Gantt chart.
How the community answered
(43 responses)- A5% (2)
- B9% (4)
- C84% (36)
- D2% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#PERT#project scheduling#network analysis#activity time estimation