In the planning of a new major manufacturing program, the greatest quality effort should be put logically in
The correct answer is D. Prevention of occurrence of substandard quality. See the full explanation below for the reasoning.
Management and Leadership in Quality Engineering
Question
In the planning of a new major manufacturing program, the greatest quality effort should be put logically in
Options
- AInspection of product.
- BNondestructive testing equipment.
- CNonconformance to specifications.
- DPrevention of occurrence of substandard quality.
How the community answered
(35 responses)- A6% (2)
- B3% (1)
- C9% (3)
- D83% (29)
Topics
#quality planning#defect prevention#manufacturing program