CLSSYB · Question #112

The Control Plan is the road map to sustaining the improvements made through the Lean Six Sigma project and should therefore involve keeping the __________ up to date as a means of supporting the…

The correct answer is C. FMEA. You've hit your limit · resets 12:50am (America/New_York)

Control Phase Basics

Question

The Control Plan is the road map to sustaining the improvements made through the Lean Six Sigma project and should therefore involve keeping the __________ up to date as a means of supporting the Response Plan in case a defect is noticed.

Options

  • AX-Y Diagram
  • BShewhart Chart
  • CFMEA
  • DCustomer Service Plan

How the community answered

(54 responses)
  • B
    2% (1)
  • C
    94% (51)
  • D
    4% (2)

Explanation

You've hit your limit · resets 12:50am (America/New_York)

Topics

#Control Plan#FMEA#Response Plan#process sustainability

Community Discussion

No community discussion yet for this question.