GAQM
CLSSYB · Question #113
To minimize waste through the application of Lean Principles we do which of the following?
The correct answer is B. Keep the work area clean and organized. You've hit your limit · resets 12:50am (America/New_York)
Improve Phase Basics
Question
To minimize waste through the application of Lean Principles we do which of the following?
Options
- ACollect sample data
- BKeep the work area clean and organized
- CCalibrate our measurement tools
- DSurvey the customer
How the community answered
(21 responses)- A5% (1)
- B90% (19)
- D5% (1)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#Lean Principles#waste elimination#5S#workplace organization
Community Discussion
No community discussion yet for this question.