Upon completion of a project a Belt must complete the ____________________ then transfer responsibility for this to the Process Owner.
The correct answer is D. Documentation Plan. You've hit your limit · resets 12:50am (America/New_York)
Control Phase Basics
Question
Upon completion of a project a Belt must complete the ____________________ then transfer responsibility for this to the Process Owner.
Options
- AFinal Process Map
- BProject Timesheet
- CTeam Briefing Paper
- DDocumentation Plan
How the community answered
(21 responses)- A5% (1)
- C5% (1)
- D90% (19)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#documentation plan#process owner#project closure#knowledge transfer