CLSSYB · Question #58
The Control Plan is created following the finalization of the Measure Phase and can be closed when?
The correct answer is C. Never, a Control Plan must stay in place. You've hit your limit · resets 12:50am (America/New_York)
Control Phase Basics
Question
The Control Plan is created following the finalization of the Measure Phase and can be closed when?
Options
- AAfter the project costs have been recouped
- BWhen the Champion says so
- CNever, a Control Plan must stay in place
- DAt the fiscal yearend of the business
How the community answered
(31 responses)- A3% (1)
- C94% (29)
- D3% (1)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#control plan#sustainability#process control#continuous improvement