The Control Plan is created following the finalization of the Measure Phase and can be closed when?

The correct answer is C. Never, a Control Plan must stay in place. You've hit your limit · resets 12:50am (America/New_York)

Control Phase Basics

Question

The Control Plan is created following the finalization of the Measure Phase and can be closed when?

Options

  • AAfter the project costs have been recouped
  • BWhen the Champion says so
  • CNever, a Control Plan must stay in place
  • DAt the fiscal yearend of the business

How the community answered

(31 responses)
  • A
    3% (1)
  • C
    94% (29)
  • D
    3% (1)

Explanation