CGEIT · Question #603
CGEIT Question #603: Real Exam Question with Answer & Explanation
Sign in or unlock CGEIT to reveal the answer and full explanation for question #603. The question stem and answer options stay visible for context.
Submitted by kevin_r· Apr 18, 2026Governance of Enterprise IT
Question
A board of directors has mandated that key performance indicators (KPIs) be developed for all IT projects that are created in support of a business objective. Which of the following MUST be reflected in the KPIs to be effective?
Options
- AFuture-state architecture
- BCritical success factors (CSFs)
- CPortfolio management principles
- DKey risk indicators (KRIs)
Unlock CGEIT to see the answer
You've previewed enough free CGEIT questions. Unlock CGEIT for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#KPIs#Critical Success Factors (CSFs)#Performance Measurement#IT Governance