Question
An ongoing project is on track according to project plan. However, a recent regulation change will have a major impact to the project. The project sponsor's NEXT step should be to:
Options
- ASeek exemption from the appropriate regulatory body
- BPerform an impact analysis and update the business case
- CSubmit the project to the IT steering committee for reapproval
- DRescope the project to remove work impacted by the regulation
Unlock CGEIT to see the answer