CGEIT · Question #57

Which of the following is the BEST course of action to enable effective resource management?

The correct answer is C. Assign resources based on business priorities.. The best course of action for effective resource management is to assign resources based on business priorities, ensuring that critical initiatives receive the necessary attention and investment.

Submitted by satoshi_tk· Apr 18, 2026IT Resources

Question

Which of the following is the BEST course of action to enable effective resource management?

Options

  • AConduct an enterprise risk assessment.
  • BImplement a cross-training program.
  • CAssign resources based on business priorities.
  • DAssign resources based on risk appetite.

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    4% (2)
  • C
    73% (33)
  • D
    16% (7)

Why each option

The best course of action for effective resource management is to assign resources based on business priorities, ensuring that critical initiatives receive the necessary attention and investment.

AConduct an enterprise risk assessment.

Conducting an enterprise risk assessment is crucial for risk management, but it's a separate activity from the operational allocation of resources, though risk can influence priorities.

BImplement a cross-training program.

Implementing a cross-training program enhances skill versatility and resilience, which supports resource management indirectly, but it doesn't directly address how resources are allocated to achieve business goals.

CAssign resources based on business priorities.Correct

Effective resource management involves allocating resources-people, budget, technology-to activities that deliver the most value to the organization. Assigning resources based on defined business priorities ensures that critical projects and initiatives aligned with strategic goals are adequately staffed and funded, maximizing the impact of limited resources and driving the enterprise towards its objectives.

DAssign resources based on risk appetite.

Assigning resources based on risk appetite is a component of risk management, determining how much risk an organization is willing to take, but it's not the primary driver for overall resource allocation to achieve business objectives.

Concept tested: Strategic resource allocation

Topics

#Resource Management#Resource Allocation#Strategic Alignment#Business Priorities

Community Discussion

No community discussion yet for this question.