While monitoring an enterprise's IT projects portfolio, it is discovered that a project is 75% complete, but all budgeted resources have been expended. Which of the following is the MOST important tas
Sign in or unlock CGEIT to reveal the answer and full explanation for question #231. The question stem and answer options stay visible for context.
Submitted by minji_kr· Apr 18, 2026Benefits Realization
Question
While monitoring an enterprise's IT projects portfolio, it is discovered that a project is 75% complete, but all budgeted resources have been expended. Which of the following is the MOST important task to perform?
Options
- AReview the IT investments.
- BReorganize the IT projects portfolio.
- CRe-evaluate the business case.
- DReview the IT governance structure.
Unlock CGEIT to see the answer
You've previewed enough free CGEIT questions. Unlock CGEIT for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project management#Cost overrun#Business case re-evaluation#IT investment viability