During planning, elicitation, and sign-off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in…
The correct answer is C. Collaboration. The correct answer isCollaboration. A key part of stakeholder engagement is ensuring that their concerns and opinions are acknowledged throughout the project. The BABOK® Guide (Chapter 4.3 - Manage Stakeholder Collaboration)states that effective collaboration ensures that…
Question
During planning, elicitation, and sign-off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in this process?
Options
- ACommunication
- BInformation
- CCollaboration
- DTrustworthiness
How the community answered
(36 responses)- A3% (1)
- B6% (2)
- C89% (32)
- D3% (1)
Explanation
The correct answer isCollaboration. A key part of stakeholder engagement is ensuring that their concerns and opinions are acknowledged throughout the project. The BABOK® Guide (Chapter 4.3 - Manage Stakeholder Collaboration)states that effective collaboration ensures that stakeholders remain engaged and contribute torequirement validation, prioritization, and decision- making. A lack of collaboration often results in stakeholder dissatisfaction and disengagement, leading to project risks.