CCBA · Question #506
The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help…
The correct answer is A. Schedule a backlog walkthrough with the two stakeholders. The BA should schedule a backlog walkthrough with the two stakeholders who do not agree on the priority of several product backlog items. This is because a backlog walkthrough is a technique that involves reviewing and discussing the product backlog items with the stakeholders…
Question
The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help move the project forward?
Options
- ASchedule a backlog walkthrough with the two stakeholders
- BConfirm the authority of the two stakeholders
- CNotify the project manager
- DApply the previous backlog priority
How the community answered
(19 responses)- A84% (16)
- C11% (2)
- D5% (1)
Explanation
The BA should schedule a backlog walkthrough with the two stakeholders who do not agree on the priority of several product backlog items. This is because a backlog walkthrough is a technique that involves reviewing and discussing the product backlog items with the stakeholders to ensure a common understanding and agreement on their priority, scope, and acceptance criteria. A backlog walkthrough can help to resolve any conflicts or disagreements among the stakeholders and move the project forward. The other options are not as effective or appropriate as scheduling a backlog walkthrough.