CCBA · Question #505
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are…
The correct answer is A. Quality control checklist. The BA should use a quality control checklist to address the project manager's concern about incomplete requirements. This is because a quality control checklist is a tool that helps to verify that the requirements meet the quality criteria and standards defined for the…
Question
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
Options
- AQuality control checklist
- BCommunication plan
- CDecision analysis
- DRisk review
How the community answered
(22 responses)- A77% (17)
- B14% (3)
- C5% (1)
- D5% (1)
Explanation
The BA should use a quality control checklist to address the project manager's concern about incomplete requirements. This is because a quality control checklist is a tool that helps to verify that the requirements meet the quality criteria and standards defined for the project. A quality control checklist can help to identify and correct any errors, omissions, inconsistencies, or ambiguities in the requirements. Using a quality control checklist can also help to avoid schedule delays caused by incomplete requirements. The other options are not directly related to checking the completeness of the requirements.