Question
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
Options
- AQuality control checklist
- BCommunication plan
- CDecision analysis
- DRisk review