CCBA · Question #351
The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information abou
The correct answer is C. Functional design specification of the existing system. The scenario describes a task that involves gathering information about a minor change to an existing system. The task requires the BA to understand the current state of the system and the requirements for the enhancement. Therefore, the BA should review the functional design spe
Question
The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information about the change. What should the BA review before the meeting?
Options
- AMinutes from the last steering committee meeting
- BOrganizational structure of the impacted department
- CFunctional design specification of the existing system
- DCurrent list of funded initiatives for the current year
How the community answered
(52 responses)- A4% (2)
- B2% (1)
- C92% (48)
- D2% (1)
Explanation
The scenario describes a task that involves gathering information about a minor change to an existing system. The task requires the BA to understand the current state of the system and the requirements for the enhancement. Therefore, the BA should review the functional design specification of the existing system before the meeting, as this document provides the details of the system's features, functions, and interfaces. Reviewing the functional design specification would help the BA to identify the scope of the change, the impact on the system, and the potential risks and issues.
Topics
Community Discussion
No community discussion yet for this question.