CBAP · Question #9

When can changes to requirements occur in a business analysis planning and monitoring assignment?

The correct answer is B. Changes to requirements can occur at any time. In business analysis, requirements are not frozen at any fixed milestone and can be proposed or updated throughout the entire project lifecycle.

Requirements Life Cycle Management

Question

When can changes to requirements occur in a business analysis planning and monitoring assignment?

Options

  • AChange to requirements can occur any time before the project scope statement is created.
  • BChanges to requirements can occur at any time.
  • CChanges to requirements can occur any time after the project's change control system has
  • DChange to requirements can occur at any time before the key stakeholders approve the

How the community answered

(13 responses)
  • A
    15% (2)
  • B
    77% (10)
  • D
    8% (1)

Why each option

In business analysis, requirements are not frozen at any fixed milestone and can be proposed or updated throughout the entire project lifecycle.

AChange to requirements can occur any time before the project scope statement is created.

Restricting changes to before the project scope statement limits change management to only the earliest project phase, which contradicts BABOK guidance on managing requirements throughout the lifecycle.

BChanges to requirements can occur at any time.Correct

The BABOK Guide recognizes that business conditions, stakeholder needs, and project circumstances can shift at any point during a project engagement. Requirements changes may be triggered by external events, new stakeholder insights, or evolving technology at any stage. This is why business analysis planning must include change management strategies that apply continuously rather than only during specific phases.

CChanges to requirements can occur any time after the project's change control system has

A change control system is a process for evaluating and approving changes, not a starting gate - requirements changes can be initiated at any time and then processed through that system.

DChange to requirements can occur at any time before the key stakeholders approve the

Stakeholder approval of requirements does not create a hard cutoff for changes; evolving business needs can necessitate revisiting requirements even after formal approval has been granted.

Concept tested: Requirements change management throughout project lifecycle

Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/babok/

Topics

#change management#requirements changes#requirements lifecycle#change control