CBAP · Question #59
The RGQ Organization utilizes a change log. What is a change log?
The correct answer is C. It is a document that tracks all characteristics and status of changes that have been received.. A change log is a document that records and tracks all changes submitted to a project or solution, including detailed characteristics of each change (such as its description, submitter, date, priority) and its current status (such as submitted, under review, approved, rejected, o
Question
The RGQ Organization utilizes a change log. What is a change log?
Options
- AIt is a document that records all change requests for the project.
- BIt is a document that tracks all unauthorized changes to the project solution.
- CIt is a document that tracks all characteristics and status of changes that have been received.
- DIt is a document that tracks the changes that have been received, including their
How the community answered
(28 responses)- A11% (3)
- B4% (1)
- C82% (23)
- D4% (1)
Explanation
A change log is a document that records and tracks all changes submitted to a project or solution, including detailed characteristics of each change (such as its description, submitter, date, priority) and its current status (such as submitted, under review, approved, rejected, or implemented). Option A is incomplete because it only mentions recording change requests, not their ongoing status or characteristics. Option B is incorrect because a change log tracks all changes - not just unauthorized ones. A change log is a comprehensive tracking tool that gives the project team full visibility into the lifecycle and attributes of every change request received.
Topics
Community Discussion