CBAP · Question #503

A business analyst (BA) is working on an initiative to decommission a legacy system and has discovered the requirement `'Ability to view policies created m the legacy system for a period of 6…

The correct answer is B. Transition Requirement. A requirement that exists only during the period of moving from a legacy system to a new system is a Transition Requirement, not a permanent solution need.

Requirements Analysis and Design Definition

Question

A business analyst (BA) is working on an initiative to decommission a legacy system and has discovered the requirement `'Ability to view policies created m the legacy system for a period of 6 months. ''How should the BA classify the requirement based on the requirements classification schema?

Options

  • AFunctional Requirement
  • BTransition Requirement
  • CNon-Functional Requirement
  • DBusiness Requirement

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    72% (26)
  • C
    8% (3)
  • D
    17% (6)

Why each option

A requirement that exists only during the period of moving from a legacy system to a new system is a Transition Requirement, not a permanent solution need.

AFunctional Requirement

Functional requirements define permanent capabilities the solution must deliver, not temporary access needs tied to a system transition window.

BTransition RequirementCorrect

Transition requirements are temporary needs that only exist during the changeover from one state to another, per the BABOK classification schema. The ability to view legacy policies for 6 months is explicitly tied to the decommissioning period and will no longer be needed once the transition is complete. This time-bounded, change-driven nature is the defining characteristic of a transition requirement.

CNon-Functional Requirement

Non-functional requirements specify quality attributes such as performance, availability, or security - not time-limited data access during a migration.

DBusiness Requirement

Business requirements describe high-level organizational goals and outcomes, not specific temporary data viewing needs during a decommission project.

Concept tested: Transition requirement classification in BABOK

Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/babok/

Topics

#transition requirements#requirements classification#legacy system#system decommission