CBAP · Question #484
In a risk assessment exercise of a software implementation program, the business analyst (BA) has successfully computed the probability of occurrence (POC) and the cost of impact for each of the…
The correct answer is B. Power surges. Negative impact to value in risk assessment is determined by multiplying probability of occurrence by cost of impact, and the risk with the highest resulting expected loss represents the greatest threat.
Question
In a risk assessment exercise of a software implementation program, the business analyst (BA) has successfully computed the probability of occurrence (POC) and the cost of impact for each of the identified risks as follows:
Which of the following will have the highest negative impact to value?
Options
- ANatural disasters
- BPower surges
- CHuman errors
- DSystem security
How the community answered
(54 responses)- A9% (5)
- B81% (44)
- C2% (1)
- D7% (4)
Why each option
Negative impact to value in risk assessment is determined by multiplying probability of occurrence by cost of impact, and the risk with the highest resulting expected loss represents the greatest threat.
Natural disasters have a lower combined expected value when probability is multiplied by cost of impact compared to power surges, resulting in a lower overall negative impact to value.
Power surges carry the highest negative impact to value because their computed expected value - probability of occurrence multiplied by cost of impact - exceeds that of the other identified risks in the assessment table. Even a moderately high probability combined with a severe cost of impact can produce an expected loss that outweighs risks with higher frequency but lower per-incident impact. This makes power surges the priority risk requiring the most immediate mitigation planning.
Human errors, despite potentially high frequency, produce a lower expected loss value when their probability is multiplied by their cost of impact compared to the power surge calculation.
System security risks yield a lower probability-times-impact product than power surges, ranking them below power surges in overall negative impact to value.
Concept tested: Risk expected value calculation probability times impact
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.