A company is in the middle of a large-scale project. Safety concerns have been brought up by several stakeholders, and this has led to numerous proposed changes. The business analyst (BA) must now ass

The correct answer is B. Urgency. When safety concerns drive proposed changes, urgency is the critical factor because safety issues may demand immediate prioritization and action.

Requirements Life Cycle Management

Question

A company is in the middle of a large-scale project. Safety concerns have been brought up by several stakeholders, and this has led to numerous proposed changes. The business analyst (BA) must now assess the impact that making these changes will have on the project. When assessing the impact of safety concerns, which of the following should be considered?

Options

  • ADesign
  • BUrgency
  • CRisk register
  • DCost/benefit analysis

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    83% (15)
  • C
    6% (1)

Why each option

When safety concerns drive proposed changes, urgency is the critical factor because safety issues may demand immediate prioritization and action.

ADesign

Design is an output artifact produced after decisions are made, not a factor considered during impact assessment of a proposed change.

BUrgencyCorrect

Urgency is the key consideration when assessing the impact of safety-related changes because safety concerns are inherently time-sensitive - delayed response can result in harm, liability, or regulatory violation. Assessing urgency determines how quickly the change must be enacted relative to the ongoing risk. This factor directly drives change prioritization, resource reallocation, and scheduling decisions within the project.

CRisk register

The risk register is a reference document that logs known risks but is not itself a consideration factor when evaluating the impact of a proposed change.

DCost/benefit analysis

Cost/benefit analysis applies broadly to all change requests but does not specifically address the time-sensitive nature inherent to safety concerns.

Concept tested: Change impact assessment - urgency of safety changes

Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/babok-v3/

Topics

#change assessment#urgency#change impact#safety requirements

Community Discussion

No community discussion yet for this question.

Full CBAP Practice