You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the…

The correct answer is C. Project manager. The project manager is responsible for writing the project scope, which defines project boundaries and deliverables, while the business analyst owns the solution scope.

Strategy Analysis

Question

You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor. Which of these stakeholders will be responsible for writing the project scope?

Options

  • ADomain subject matter expert
  • BBusiness analyst
  • CProject manager
  • DSponsor

How the community answered

(41 responses)
  • A
    12% (5)
  • B
    5% (2)
  • C
    78% (32)
  • D
    5% (2)

Why each option

The project manager is responsible for writing the project scope, which defines project boundaries and deliverables, while the business analyst owns the solution scope.

ADomain subject matter expert

The domain subject matter expert contributes knowledge about the business domain but does not own or write the project scope.

BBusiness analyst

The business analyst is responsible for the solution scope, not the project scope; writing project scope falls under project management, not business analysis.

CProject managerCorrect

The project manager is accountable for defining and documenting the project scope as part of project scope management, covering what work is and is not included in the project. This is distinct from the solution scope, which describes the solution to the business problem and is owned by the business analyst. Confusing the two scopes is a common error - the BA defines the solution, the PM defines the project.

DSponsor

The sponsor authorizes and funds the project and approves the scope but delegates the actual writing of the project scope to the project manager.

Concept tested: Project scope vs solution scope ownership

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#solution scope#project scope#stakeholder roles#project manager

Community Discussion

No community discussion yet for this question.

Full CBAP Practice