CBAP · Question #257

CBAP Question #257: Real Exam Question with Answer & Explanation

The correct answer is B. Project manager. Once requirements are signed off and a project is chartered, the project manager takes ownership of translating solution scope into project scope.

Question

You have completed the requirements documentation and the stakeholders have signed off on the requirements. Now the requirements are advancing into a project as your organization has chartered a project based on the identified requirements. What stakeholder is now responsible for assessing the solution scope to determine the project scope?

Options

  • AProject sponsor
  • BProject manager
  • CBusiness analyst
  • DKey stakeholders

Explanation

Once requirements are signed off and a project is chartered, the project manager takes ownership of translating solution scope into project scope.

Common mistakes.

  • A. The project sponsor authorizes and funds the project but is not responsible for the technical assessment of solution scope to define project scope.
  • C. The business analyst defines solution scope during requirements development, but once the project is chartered, scope assessment responsibility transfers to the project manager.
  • D. Key stakeholders provide input and approval on requirements but do not hold formal responsibility for assessing solution scope to determine project scope.

Concept tested. Project manager responsibility for project scope definition

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok