CBAP · Question #252
CBAP Question #252: Real Exam Question with Answer & Explanation
The correct answer is A. List of identified risks. The list of identified risks is not a formal input to the plan business analysis activities process; the recognized inputs are the business analysis approach, organizational process assets, and the stakeholder list with roles and responsibilities.
Question
Options
- AList of identified risks
- BOrganizational process assets
- CBusiness analysis approach
- DStakeholder list, roles, and responsibilities
Explanation
The list of identified risks is not a formal input to the plan business analysis activities process; the recognized inputs are the business analysis approach, organizational process assets, and the stakeholder list with roles and responsibilities.
Common mistakes.
- B. Organizational process assets - including templates, historical records, and lessons learned - are a recognized and defined input to plan business analysis activities.
- C. The business analysis approach is a core input that defines the overall methodology, timing, and formality of business analysis work on the project.
- D. The stakeholder list, roles, and responsibilities is a defined input that informs who will be engaged and how during business analysis planning.
Concept tested. Inputs to plan business analysis activities process
Reference. https://www.iiba.org/standards-and-resources/babok/
Community Discussion
No community discussion yet for this question.