The correct answer is A. Requirements management plan. The requirements management plan is the specific business analysis artifact that defines how requirements and solution scope will be elicited, documented, traced, and controlled throughout the project.
Question
What business analysis plan defines the process to be followed in managing the solution scope and requirements?
Options
- ARequirements management plan
- BScope management plan
- CChange management plan
- DProject management plan
Explanation
The requirements management plan is the specific business analysis artifact that defines how requirements and solution scope will be elicited, documented, traced, and controlled throughout the project.
Common mistakes.
- B. The scope management plan is a project management artifact focused on defining and controlling the overall project scope, not specifically on the processes for managing solution requirements.
- C. The change management plan addresses how organizational changes will be communicated and adopted by people, not how requirements will be tracked and governed.
- D. The project management plan is a high-level umbrella document covering all aspects of project delivery - it may reference a requirements management plan as a subsidiary, but is itself not a business analysis planning document.
Concept tested. Requirements management plan purpose in business analysis
Reference. https://www.pmi.org/learning/library/requirements-management-plan-scope-5725