CBAP · Question #221
When do change requests generally increase in a project?
The correct answer is D. Towards the end of the project. Change requests typically surge near project completion because stakeholders can see tangible deliverables and identify gaps between expectations and reality.
Question
When do change requests generally increase in a project?
Options
- ADuring the project's launch.
- BTowards the beginning of the project.
- CDuring the project scope management processes.
- DTowards the end of the project.
How the community answered
(58 responses)- A3% (2)
- B10% (6)
- C7% (4)
- D79% (46)
Why each option
Change requests typically surge near project completion because stakeholders can see tangible deliverables and identify gaps between expectations and reality.
Project launch is characterized by initiation activities and charter development, not scope-driven change requests from stakeholders.
At the beginning of a project, requirements are still being gathered and scope is not yet baselined, so formal change requests are not yet applicable.
Scope management processes are used to control changes, not a phase when change requests inherently increase in volume.
As a project nears completion, stakeholders gain clearer visibility into the final product, which reveals misalignments between delivered scope and original expectations. This phenomenon is well-documented in project management: the cost and frequency of changes escalate late in the project lifecycle because the product is nearly finished and deviations become apparent. Late-stage changes are also the most expensive to implement, making this phase the most critical for change control.
Concept tested: Change request frequency in project lifecycle