CBAP · Question #211
All of the following stakeholders participate in the prioritization of requirements except for which one?
The correct answer is B. Project team. According to the BABOK Guide, the project team as a collective body is not listed as a distinct stakeholder that participates in requirements prioritization.
Question
All of the following stakeholders participate in the prioritization of requirements except for which one?
Options
- AImplementation subject matter expert
- BProject team
- CDomain subject matter expert
- DProject manager
How the community answered
(19 responses)- A11% (2)
- B79% (15)
- C5% (1)
- D5% (1)
Why each option
According to the BABOK Guide, the project team as a collective body is not listed as a distinct stakeholder that participates in requirements prioritization.
Implementation subject matter experts participate in prioritization because they provide critical input on technical feasibility and effort required to implement each requirement.
The BABOK Guide identifies specific stakeholder roles that participate in requirements prioritization - including domain SMEs, implementation SMEs, project managers, customers, and end users - but does not list the project team as a separate participating stakeholder. Individual roles within the project team may participate, but the project team collectively is not enumerated as a prioritization stakeholder.
Domain subject matter experts participate in prioritization because they understand the business value and necessity of each requirement within the problem domain.
The project manager participates in prioritization because they must balance scope, schedule, and resource constraints when determining requirement priority.
Concept tested: Requirements prioritization stakeholder participation
Source: https://www.iiba.org/career-resources/a-business-analysis-body-of-knowledge/