CBAP · Question #165
The ____, an output of the define scope process, does document the process and criteria for accepting completed products.
The correct answer is C. Project scope statement. The Project Scope Statement, produced by the Define Scope process, formally documents deliverables and the acceptance criteria for completed products.
Question
The ____, an output of the define scope process, does document the process and criteria for accepting completed products.
Options
- AStatement of Work
- BContract
- CProject scope statement
- DProject management plan
How the community answered
(24 responses)- A4% (1)
- B4% (1)
- C83% (20)
- D8% (2)
Why each option
The Project Scope Statement, produced by the Define Scope process, formally documents deliverables and the acceptance criteria for completed products.
A Statement of Work describes the work a vendor or contractor must perform and is an input to procurement processes, not an output of Define Scope.
A Contract is a legally binding agreement between buyer and seller used in procurement and is unrelated to the Define Scope process output.
The Project Scope Statement is the key output of the Define Scope process in the PMBOK framework. It explicitly documents the project scope description, major deliverables, exclusions, assumptions, constraints, and the criteria used to accept completed products. No other process output consolidates acceptance criteria in this way.
The Project Management Plan is a high-level integrating document covering all subsidiary plans and is not the specific Define Scope output that records acceptance criteria.
Concept tested: Define Scope process output and acceptance criteria
Source: https://www.pmi.org/pmbok-guide-standards