CAPM · Question #523
When would be the most appropriate time to address the issue raised on the iteration review?
The correct answer is B. In the sprint retrospective. In Scrum, each ceremony has a distinct purpose. The iteration (sprint) review focuses on inspecting the product increment and gathering stakeholder feedback. The sprint retrospective, which immediately follows, is specifically designed to inspect how the team worked and…
Question
Options
- AIn the customer prototype demo
- BIn the sprint retrospective
- CAfter the backlog refinement
- DAfter the iteration planning
How the community answered
(49 responses)- A4% (2)
- B92% (45)
- C2% (1)
- D2% (1)
Explanation
In Scrum, each ceremony has a distinct purpose. The iteration (sprint) review focuses on inspecting the product increment and gathering stakeholder feedback. The sprint retrospective, which immediately follows, is specifically designed to inspect how the team worked and identify process improvements. Issues surfaced during the iteration review about team performance, process problems, or collaboration barriers belong in the retrospective-the dedicated forum for 'how we work.' Customer demos focus on product presentation. Backlog refinement and iteration planning address future work, not past process issues.