nerdexam
PMIPMI

CAPM · Question #504

CAPM Question #504: Real Exam Question with Answer & Explanation

The correct answer is B: Refine the task list, incorporating tasks not completed in previous iterations.. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

A product owner and team members are working on tasks to be completed in the next project iteration. What should they do at this point in the project?

Options

  • AFollow the plan as initially designed by the team and stakeholders.
  • BRefine the task list, incorporating tasks not completed in previous iterations.
  • CShorten the delivery time of the next iteration in order to increase the management reserve.
  • DPerform an iteration retrospective with the team.

Topics

#Agile Iteration Planning#Product Backlog Refinement#Agile Roles#Unfinished Work Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions