PMIPMI
CAPM · Question #504
CAPM Question #504: Real Exam Question with Answer & Explanation
The correct answer is B: Refine the task list, incorporating tasks not completed in previous iterations.. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
A product owner and team members are working on tasks to be completed in the next project iteration. What should they do at this point in the project?
Options
- AFollow the plan as initially designed by the team and stakeholders.
- BRefine the task list, incorporating tasks not completed in previous iterations.
- CShorten the delivery time of the next iteration in order to increase the management reserve.
- DPerform an iteration retrospective with the team.
Topics
#Agile Iteration Planning#Product Backlog Refinement#Agile Roles#Unfinished Work Management
Community Discussion
No community discussion yet for this question.