CAPM · Question #504

A product owner and team members are working on tasks to be completed in the next project iteration. What should they do at this point in the project?

The correct answer is B. Refine the task list, incorporating tasks not completed in previous iterations.. During iteration planning, the team should refine the upcoming task list by incorporating incomplete work from previous iterations to ensure nothing is lost and priorities are re-assessed.

Agile Frameworks/Methodologies

Question

A product owner and team members are working on tasks to be completed in the next project iteration. What should they do at this point in the project?

Options

  • AFollow the plan as initially designed by the team and stakeholders.
  • BRefine the task list, incorporating tasks not completed in previous iterations.
  • CShorten the delivery time of the next iteration in order to increase the management reserve.
  • DPerform an iteration retrospective with the team.

How the community answered

(34 responses)
  • B
    94% (32)
  • C
    3% (1)
  • D
    3% (1)

Why each option

During iteration planning, the team should refine the upcoming task list by incorporating incomplete work from previous iterations to ensure nothing is lost and priorities are re-assessed.

AFollow the plan as initially designed by the team and stakeholders.

Following the plan as initially designed ignores the adaptive nature of iterative development and prevents the team from incorporating learnings and carry-over work.

BRefine the task list, incorporating tasks not completed in previous iterations.Correct

Iteration planning involves reviewing and refining the backlog items for the next sprint, which includes pulling in tasks that were started but not completed in prior iterations. Incorporating unfinished work ensures continuity, accurate capacity planning, and that previously committed value is delivered, which is a standard agile practice during sprint or iteration planning ceremonies.

CShorten the delivery time of the next iteration in order to increase the management reserve.

Shortening delivery time to increase management reserve is not a valid iteration planning practice and conflates schedule buffers with iteration cadence.

DPerform an iteration retrospective with the team.

An iteration retrospective occurs at the end of a completed iteration to reflect on the process, not at the start of planning the next one.

Concept tested: Iteration planning with carryover tasks in agile

Source: https://www.pmi.org/pmbok-guide-standards/practice-guides/agile

Topics

#Agile Iteration Planning#Product Backlog Refinement#Agile Roles#Unfinished Work Management

Community Discussion

No community discussion yet for this question.