nerdexam
PMI

CAPM · Question #303

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria

The correct answer is A. Definition of done (DoD). The Definition of Done (DoD) is a shared, agreed-upon checklist of all criteria that a deliverable must satisfy before it is considered complete and ready for customer use. The team used the DoD to verify that the presented deliverables met all required criteria before the demons

Agile Frameworks/Methodologies

Question

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria of the project. Which of the following elements is the team using?

Options

  • ADefinition of done (DoD)
  • BBurndown chart
  • CDefinition of ready (DoR)
  • DBacklog refinement

How the community answered

(35 responses)
  • A
    89% (31)
  • B
    3% (1)
  • C
    6% (2)
  • D
    3% (1)

Explanation

The Definition of Done (DoD) is a shared, agreed-upon checklist of all criteria that a deliverable must satisfy before it is considered complete and ready for customer use. The team used the DoD to verify that the presented deliverables met all required criteria before the demonstration. The Definition of Ready (DoR) is a different artifact - it defines the criteria a backlog item must meet before the team can begin working on it (not when work is finished). A burndown chart tracks remaining work over time, and backlog refinement is the ongoing process of updating and prioritizing the product backlog.

Topics

#Definition of Done#Agile Practices#Deliverable Completion#Customer Acceptance

Community Discussion

No community discussion yet for this question.

Full CAPM Practice