nerdexam
PMIPMI

CAPM · Question #285

CAPM Question #285: Real Exam Question with Answer & Explanation

The correct answer is B: Add the stakeholder to the stakeholder register and add the risk to the risk register.. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Options

  • AMake sure proper testing gets completed to minimize the risk highlighted.
  • BAdd the stakeholder to the stakeholder register and add the risk to the risk register.
  • CIgnore the risk from this stakeholder as this stakeholder never showed up at the start of the project.
  • DAdd this risk to the lessons learned register on project completion.

Topics

#Stakeholder Management#Risk Management#Project Documents#Project Execution

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions