PMIPMI
CAPM · Question #284
CAPM Question #284: Real Exam Question with Answer & Explanation
The correct answer is B: Two of the team members have been working in silos using different methods to validate their performance.. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates. Which of the following changes has caused this loss in productivity?
Options
- AThe team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.
- BTwo of the team members have been working in silos using different methods to validate their performance.
- CTwo of the team members were asked to do multitasking, which they did not do in the previous two sprints.
- DThe team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.
Topics
#Agile Team Dynamics#Team Collaboration#Productivity Loss#Adaptive Project Management
Community Discussion
No community discussion yet for this question.