Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

Options

  • ADiane
  • BRisk owner
  • CSubject matter expert
  • DProject sponsor