Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk

The correct answer is B. Risk owner. During risk planning, each identified risk is assigned a risk owner - the individual responsible for monitoring that risk and executing the preplanned response if it materializes. Assigning risk ownership ensures accountability and clear escalation paths. The project manager (Cho

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

Options

  • ADiane
  • BRisk owner
  • CSubject matter expert
  • DProject sponsor

How the community answered

(34 responses)
  • B
    91% (31)
  • C
    6% (2)
  • D
    3% (1)

Explanation

During risk planning, each identified risk is assigned a risk owner - the individual responsible for monitoring that risk and executing the preplanned response if it materializes. Assigning risk ownership ensures accountability and clear escalation paths. The project manager (Choice A) oversees the overall risk management process but does not personally execute every response. Subject matter experts (Choice C) may provide input but are not the designated responders unless assigned as risk owners. The project sponsor (Choice D) is involved in high-level decisions, not day-to-day risk response execution.

Topics

#Risk Management#Risk Response#Risk Owner#Roles and Responsibilities