nerdexam
(ISC)2

CAP · Question #381

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have…

The correct answer is D. Risk register. The risk register is the central document used to record all details about identified risks, including their descriptions, probability, impact, risk owners, and - critically - the planned risk responses such as mitigation strategies. The risk management plan describes the…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

Options

  • AProject management plan
  • BRisk management plan
  • CRisk log
  • DRisk register

How the community answered

(27 responses)
  • B
    4% (1)
  • C
    4% (1)
  • D
    93% (25)

Explanation

The risk register is the central document used to record all details about identified risks, including their descriptions, probability, impact, risk owners, and - critically - the planned risk responses such as mitigation strategies. The risk management plan describes the processes and methodologies for how risks will be managed (the framework), not the actual risks themselves. The project management plan is a high-level umbrella document. 'Risk log' is sometimes used informally but 'risk register' is the standard PMI/PMBOK term for where individual risk responses are documented.

Topics

#Risk Management#Risk Register#Mitigation Planning#Project Documentation

Community Discussion

No community discussion yet for this question.

Full CAP Practice