(ISC)2(ISC)2
CAP · Question #381
CAP Question #381: Real Exam Question with Answer & Explanation
The correct answer is D: Risk register. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?
Options
- AProject management plan
- BRisk management plan
- CRisk log
- DRisk register
Topics
#Risk Management#Risk Register#Mitigation Planning#Project Documentation
Community Discussion
No community discussion yet for this question.