(ISC)2(ISC)2
CAP · Question #168
CAP Question #168: Real Exam Question with Answer & Explanation
The correct answer is A: Uncertainty in values such as duration of schedule activities. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
Ned is the project manager of the HNN project for your company. Ned has asked you to help him complete some probability distributions for his project. What portion of the project will you most likely use for probability distributions?
Options
- AUncertainty in values such as duration of schedule activities
- BBias towards risk in new resources
- CRisk probabilityand impact matrixes
- DRisk identification
Topics
#Risk Analysis#Probability Distributions#Uncertainty Modeling#Project Management
Community Discussion
No community discussion yet for this question.