nerdexam
(ISC)2

CAP · Question #168

Ned is the project manager of the HNN project for your company. Ned has asked you to help him complete some probability distributions for his project. What portion of the project will you most…

The correct answer is A. Uncertainty in values such as duration of schedule activities. Probability distributions (e.g., triangular, beta/PERT, normal distributions) are used in quantitative risk analysis to represent uncertainty in continuous variables such as activity durations, resource costs, or quantities. They define the range of possible values and the…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Ned is the project manager of the HNN project for your company. Ned has asked you to help him complete some probability distributions for his project. What portion of the project will you most likely use for probability distributions?

Options

  • AUncertainty in values such as duration of schedule activities
  • BBias towards risk in new resources
  • CRisk probabilityand impact matrixes
  • DRisk identification

How the community answered

(18 responses)
  • A
    89% (16)
  • C
    6% (1)
  • D
    6% (1)

Explanation

Probability distributions (e.g., triangular, beta/PERT, normal distributions) are used in quantitative risk analysis to represent uncertainty in continuous variables such as activity durations, resource costs, or quantities. They define the range of possible values and the likelihood of each outcome. Tools like Monte Carlo simulation sample from these distributions thousands of times to produce a probability distribution of overall project cost or schedule outcomes. They are not used for probability-impact matrices (Choice C, which is qualitative), risk identification (Choice D), or resource bias assessments (Choice B).

Topics

#Risk Analysis#Probability Distributions#Uncertainty Modeling#Project Management

Community Discussion

No community discussion yet for this question.

Full CAP Practice