nerdexam
(ISC)2(ISC)2

CAP · Question #168

CAP Question #168: Real Exam Question with Answer & Explanation

The correct answer is A: Uncertainty in values such as duration of schedule activities. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Ned is the project manager of the HNN project for your company. Ned has asked you to help him complete some probability distributions for his project. What portion of the project will you most likely use for probability distributions?

Options

  • AUncertainty in values such as duration of schedule activities
  • BBias towards risk in new resources
  • CRisk probabilityand impact matrixes
  • DRisk identification

Topics

#Risk Analysis#Probability Distributions#Uncertainty Modeling#Project Management

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions