Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?

Options

  • ARisk identification
  • BPerform qualitative analysis
  • CPerform quantitative analysis
  • DRisk Breakdown Structure creation

Unlock CAP to see the answer

You've previewed enough free CAP questions. Unlock CAP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk management#Qualitative risk analysis#Risk prioritization#RMF process