Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analys
The correct answer is B. Perform qualitative analysis. Qualitative risk analysis is the process of prioritizing risks for further analysis or action by assessing and combining each risk's probability of occurrence and its impact on project objectives. This is done using tools like the Probability and Impact Matrix, risk urgency asses
Question
Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?
Options
- ARisk identification
- BPerform qualitative analysis
- CPerform quantitative analysis
- DRisk Breakdown Structure creation
How the community answered
(34 responses)- B94% (32)
- C3% (1)
- D3% (1)
Explanation
Qualitative risk analysis is the process of prioritizing risks for further analysis or action by assessing and combining each risk's probability of occurrence and its impact on project objectives. This is done using tools like the Probability and Impact Matrix, risk urgency assessment, and risk categorization. It is a subjective, relatively quick process compared to quantitative analysis. Quantitative analysis (Choice C) would involve numerical modeling of those risks. Risk identification (Choice A) precedes both analysis processes. A Risk Breakdown Structure (Choice D) is a hierarchical grouping of risk categories, not a prioritization process.